Six Road never Constructed In FY 2023/24 In Sironko District - Minister
The state Minister for Economic Monitoring, Hon Beatrice Akello, has directed the State House Aunti-Corruption Unit to investigate the district engineering department of Sironko after the team while inspecting the roads found out that 6 roads supposed to have been constructed in the last final year 2023 to 2024 have never been worked on yet government released the funds for the one billion meant and 50% of the money for last financial year has not been used The Minister revealed that all the road are in the terrible state have been abandoned and this is the second quarter of this year
She refuted the allegations by the district engineer that they have been receiving heavy rains for over a year that have hampered the construction of works
The Minister also visited the micro irrigation scheme in Mutufu town council which is not yet complete, she also inspected the Buhugu milk cooler that has not been operating for long blaming those who designed the project that they did not consult and the community is now demanding for maize mile because have no cows to sustain supply the milk cooler
The Minister later visited the Buweri administrative house that has stalled at foundation level for over 3 years at the cost of 17 million She also directed the State Aunt-corruption Unit to investigate all the projects that are incomplete
She revealed that the they have got information that the Wendi agents are conveying with the SACO leaders to solicit bribes from beneficiaries of PDM and Emyooga that they should be brought to book.
Andrew Wasukira district engineer explained that he has delayed to work on the roads due to the heavy rains that has been in the district for over one year Dennis Ephraim Balwanireghe RDC Sironko blamed the civil servants for the shoddy in the district arguing that government sends a lot of money in the district but of the projects especially roads are impassable which he blamed
On the district engineering department Herbert Musika councilor Nalusla sub county revealed that most of the roads are in the sorry state and even most of the projects that government has put out, money has been put to waste and most of the civil servants have no will to work .
The minister is in the region investigating government projects